Especially in industries where hot works are not easily permitted, the implementation of pipeline reinforcement via cold repair works are useful in the repair and rehabilitation works of pipelines.
Pipeline Data & Operating Conditions
Before carrying out
an effective pipeline rehabilitation and reinforcement work, pipeline data and
operating conditions are gathered. These data are reviewed and evaluated under international
standards and guidelines such as ASME PCC2 and ISO 24817 standards and
requirements, to design an effective and suitable pipeline repair and
reinforcement solution.
Detailed
Engineering Calculation and Application Method of Statement
Based on the
pipeline data gathered, the manufacturer would design and provide a detailed
engineering calculation and application technique for the pipeline repair and
rehabilitation works. It is also necessary to ensure that the applicator is
well-trained to apply the pipe repair kit products as well as a site risk
assessment has been performed prior to work commencement. Proper Personnel
Protective Equipment should be worn and risk mitigating/ reducing steps
employed to minimize or avoid all unnecessary risks.
Step 1 – Preparing, Cleaning and Roughening of Pipe Surface
Pipe surface should be cleaned and prepared to minimum standard of St2.5. This is to ensure good bonding between the repair resin with the substrate (pipe surface). The pipe surface profile is also roughed to meet the minimum of 60 microns roughness. Once the pipe surface has been cleaned and roughened, pipeline repair and rehabilitation works should commence immediately.
Pipe surface should be cleaned and prepared to minimum standard of St2.5. This is to ensure good bonding between the repair resin with the substrate (pipe surface). The pipe surface profile is also roughed to meet the minimum of 60 microns roughness. Once the pipe surface has been cleaned and roughened, pipeline repair and rehabilitation works should commence immediately.
Step 2 - Rebuilding to ensure Flushing of Pipe Surface
The first step in all rehabilitation works is to ensure that all pipe surfaces have been rebuilt so as to ensure surface being flush. The resin or repair putty compound is well-mixed in accordance to manufacturer’s instructions and applied onto the affected surfaces while ensuring there are no air entrapments. The repair compound is applied according to the required coating thickness and repair length specified in engineering calculation.
The first step in all rehabilitation works is to ensure that all pipe surfaces have been rebuilt so as to ensure surface being flush. The resin or repair putty compound is well-mixed in accordance to manufacturer’s instructions and applied onto the affected surfaces while ensuring there are no air entrapments. The repair compound is applied according to the required coating thickness and repair length specified in engineering calculation.
Step
3 – Pipeline Reinforcement via Pipe Wrapping
The final step is to pipeline repair and reinforcement is wrapping of the reinforcement repair tape. Start wrapping the reinforcement repair tape over the pipe circumference just before the defect location. At each round of wrapping, wrap the pipe as tightly and evenly as possible while pulling with sufficient strength. Ensure there is 50% overlap to the previous wrapping layer. Repeat the wrapping based on the Engineering Calculation Report. The wrapping direction can be alternated between subsequent layers of wrapping to increase its final mechanical strength.
The final step is to pipeline repair and reinforcement is wrapping of the reinforcement repair tape. Start wrapping the reinforcement repair tape over the pipe circumference just before the defect location. At each round of wrapping, wrap the pipe as tightly and evenly as possible while pulling with sufficient strength. Ensure there is 50% overlap to the previous wrapping layer. Repeat the wrapping based on the Engineering Calculation Report. The wrapping direction can be alternated between subsequent layers of wrapping to increase its final mechanical strength.
Inspection of Pipeline Repair & Reinforcement Works
Inspect the reinforced pipeline for any visual defects. Check that the repair thickness and length complies with the requirements stated in the Engineering Calculation. Allow the repaired area to be cured for several hours and the reinforcement work is completed.
Inspect the reinforced pipeline for any visual defects. Check that the repair thickness and length complies with the requirements stated in the Engineering Calculation. Allow the repaired area to be cured for several hours and the reinforcement work is completed.